The federal government has agreed to review the design of the proposed Panjgur Dam in Balochistan following concerns raised by senators regarding its potential impact on agricultural land, date palm orchards, and traditional irrigation systems.

During a meeting of the Senate Subcommittee on Problems of Less Developed Areas at Parliament House, Senator Jan Muhammad Buledi questioned why the impact on existing irrigation systems had not been properly assessed during the project’s planning. Buledi stated, "Public funds spent on development schemes should bring tangible benefits to local communities rather than create additional difficulties." He suggested that the government explore smaller dams as an alternative to the current proposal.

National Party MNA Pullain Baloch also called for a detailed assessment of the proposed canal system’s impact on local livelihoods, settlements, and farmland. He emphasized that development projects in Balochistan should primarily serve local communities and must not damage their economic activities or agricultural resources.

In response to these concerns, officials from the Planning Division assured the committee that the dam’s design would be reviewed in consultation with the Irrigation Department. The project director informed the committee that Panjgur previously utilized 118 traditional underground irrigation channels, known as karezes, which supplied water to approximately 6,000 acres of farmland. However, the director revealed that solar-powered water extraction systems have affected 72 of these channels, and water flows in 34 karezes have declined by more than 50 percent over the past two years.

The proposed dam is designed to be 33 meters high and is intended to irrigate approximately 25,000 acres of land. The project includes a 30-kilometer canal on the left side and a 9.8-kilometer canal on the right side. To protect thousands of date palms and agricultural land, officials stated the original open-canal design has been revised to a pipeline-based water supply system. While this revised design has been finalized, a cost estimate from China is still awaited.

The subcommittee also reviewed the Gish Kaur Dam project and directed the Water and Power Development Authority (WAPDA) to submit a report on its potential impact on downstream agriculture connected with Kech Kaur and the possible reduction in water reaching the Mirani Dam.

Additionally, the committee reviewed the pace of implementation of the Aghaz-i-Haqooq-i-Balochistan Package and recruitment against the province’s quota in federal ministries. Senator Buledi noted that the Establishment Division informed the committee that complete records of appointments of candidates from Balochistan in federal institutions were not available. Consequently, the subcommittee directed the Establishment Division to submit a comparative report covering appointments, vacant positions, and allocated quotas.

Federal Minister for Planning Ahsan Iqbal stated that since Balochistan’s uplift was closely linked to the country’s overall progress, the government has committed itself to accelerating development in the province.