The cost of fuel for generating electricity in Pakistan has surged by 34 percent during the first four months of fiscal year 2027. According to Topline Research, the average fuel cost reached Rs. 10.2 per unit between July and October FY2027, a significant rise from the Rs. 7.6 per unit recorded during the same period last year.

The data shows that this increase in cost occurred despite a modest 6 percent rise in cumulative power generation. During the first four months of FY2027, the country generated 54,024 gigawatt hours (GWh) of electricity, compared to 50,818 GWh in the same period of the previous year.

In October 2026 alone, the fuel cost rose 25 percent year over year and 14 percent month over month, reaching Rs. 10.6 per unit. During that month, Pakistan generated 10,743 GWh of electricity, which was a 9 percent increase from the 9,885 GWh produced in October last year. However, output in October 2026 was 19 percent lower than the 13,217 GWh produced in September.

The composition of the national power mix saw dramatic shifts in October. Imported coal based power generation saw a sharp increase of 237 percent year over year to 1,569 GWh, raising its share of the national mix to 14.6 percent from 4.7 percent a year earlier. Furnace oil based generation surged 631 percent to 351 GWh, while wind power generation increased 71 percent to 316 GWh.

Gas based generation also rose 20 percent to 1,090 GWh. Conversely, RLNG based generation declined 61 percent to 757 GWh, which reduced its share in the power mix to 7 percent from 19.7 percent last year. Hydropower generation saw a 4 percent increase to 2,818 GWh, while nuclear generation fell 4 percent to 2,090 GWh.