The Khyber Pakhtunkhwa government is preparing to launch an Rs 18.58 billion gravity-flow water supply project in Mansehra. According to documents available with Wealth Pakistan, the initiative aims to resolve the city's increasing drinking water shortage and provide a sustainable supply for residents until 2040.
The project is designed to accommodate an estimated population of 201,249, which exceeds the city's current population of 138,143. Currently, Mansehra receives only 0.58 million imperial gallons per day (MGD) of water, while the projected daily requirement is 5.49 MGD.
The plan involves transporting raw water from Neeli Nadi via a 64.7-kilometre-long, 600-millimetre-diameter mild steel pipeline. By using gravity flow, the system will eliminate the need for conventional pumping along the transmission route. The water will be processed at a treatment plant with a capacity of 240 litres per second, which is approximately 4.6 MGD, before entering a distribution network.
The project scope includes laying 309 kilometres of distribution pipelines, installing consumer water meters, and developing 15 high-ground reservoirs. This includes eight new facilities and seven existing ones. Other components include a 23.8-kilometre treated-water transmission system, intake structures, access roads, cross-drainage works, and modern monitoring equipment.
Of the total Rs 18,583.41 million cost, Rs 17,144.09 million, or 92.3 per cent, is allocated to direct construction and development. The remaining Rs 1,439.33 million will cover indirect expenses. The 64.7-kilometre raw water transmission pipeline is the largest single component, costing an estimated Rs 7.85 billion. Additionally, Rs 2.76 billion is earmarked for geological hazard management and landslide mitigation due to the mountainous terrain.
The project will be jointly financed by the provincial government and the Saudi Fund for Development (SFD). The KP government will contribute Rs 11.23 billion (60.4 per cent), while the SFD will provide Rs 7.35 billion (39.6 per cent).
The scheme has a long planning history, with feasibility studies and engineering designs prepared in 2011-12. An initial PC-I worth Rs 4.4 billion was prepared in 2014, and the SFD agreed to finance the scheme in January 2019. A revised PC-I was approved during 2022-23, with administrative approval granted on April 16, 2024. Agreements were signed in 2025. The project has a 42-month implementation period, with a completion target of October 16, 2028.
Upon completion, the project is expected to improve access to safe drinking water, reduce groundwater reliance, and strengthen public health by providing a sustainable supply for the growing population.