The Capital Development Authority (CDA) announced on Monday, November 23, that development work on the Sangjani Interchange project and the Margalla Avenue extension from N-5 to M-1 has reached 43 per cent completion.
The project involves an approximately 2.7-kilometre extension of Margalla Avenue within the Islamabad Capital Territory (ICT) limits. According to a CDA statement, work is currently underway on various sections of the road, as well as connecting service roads, loops, and ramps.
The authority stated that work on the loops and ramps is nearing completion. Regarding the underpass, the structural work—including the footing slabs and concrete walls—is finished, and earth filling on both sides of the structure is expected to be completed shortly.
At the Sangjani Interchange, the CDA reported that piling work is finished while steel fixing is currently in progress. Piling and girder work have also been completed, with excavation work nearing completion. Additionally, piling and excavation for the abutments on both sides of the N-5 bridge have been finished.
Of the five culverts included in the project, the CDA said four are complete, with work continuing on the final one.
CDA Chairman and Chief Commissioner Islamabad Sohail Ashraf has directed the concerned authorities to ensure the project is finished within the stipulated timeframe while maintaining construction quality. Ashraf said the project would serve as an important gateway for people travelling to Islamabad from other cities, particularly Khyber Pakhtunkhwa, and improve access to Islamabad International Airport for commuters travelling within and outside the capital.