Pakistan plans to invest an estimated $5.7 billion to upgrade its five major oil refineries, a move that could nearly double domestic petrol production and increase high-speed diesel output by around 47 percent, according to an OGRA document.

The modernization projects are expected to raise daily petrol production from 10,702 tonnes to 21,251 tonnes. High-speed diesel output is projected to increase from 21,237 tonnes to 31,288 tonnes. The upgrades will cover Attock Refinery, Pakistan Refinery Limited (PRL), National Refinery Limited (NRL), Cnergyico and PARCO.

All five refineries are targeting improvements in petrol and diesel quality to Euro-V standards after modernization. The investment is aimed at strengthening Pakistan’s domestic refining capacity, reducing dependence on imported petroleum products and improving the country’s foreign exchange position. The projects are also expected to save approximately $1 billion in foreign exchange annually by reducing reliance on imported fuel.

The OGRA document provides specific investment figures and timelines for each refinery:

PARCO’s upgrade is estimated to cost $1.4 billion, with completion targeted for 2029.

Pakistan Refinery Limited is expected to invest $1.7 billion in its modernization project, which is scheduled for completion by 2028.

National Refinery Limited’s upgrade is estimated to cost $1 billion, with a target completion date of 2029.

Cnergyico is also expected to invest $1 billion in its refinery upgrade, which is scheduled to be completed by 2030.

Attock Refinery’s modernization project is estimated to cost $600 million, with completion targeted for 2029.

The five projects are expected to be completed between 2028 and 2030.